Hiawatha projects update

By robb, June 11, 2014 10:29 am

Update 06.13:  Expect Hiawatha to be reduced to one lane Tuesday and Wednesday next week for median tree planting.

Project work along Hiawatha Avenue will be continuing for the next few weeks and should be completed by Independence Day.

Hiawatha Intersection Improvements: A few final areas of concrete need to be poured.  APS signals still need to be installed at the intersections.  Striping of the crosswalks and bike lanes along 32nd Street will start next week.

Hiawatha Avenue Landscaping: Around 165 trees and stumps have been removed from the corridor.  Tree planting will begin later this week in the boulevards.  Median tree planting is planned for next week and will require Hiawatha Ave to be reduced to one lane of traffic [lane closures are limited to off-peak hours].

Thanks for your patience as we work toward a more pedestrian, bike, transit, and vehicle-friendly Hiawatha Avenue.

Hiawatha Ave Construction Image